Project Description

HEC was engaged by PWGSC to develop a concept and complete the detailed design of repairs to the existing severely deteriorated SSP bulkhead breakwater structure at the Skinners Pond facility. The project included the provision of new SSP outside of the existing SSP, new walers and tie rods, concrete dead man tie backs, and the installation of a new rubblemound rock breakwater/wave break directly adjacent to the rehabilitated structure, and the installation of a new concrete deck.

Client: Public Works and Government Services Canada

Value: $2M (Approximate Construction Value)

Year: 2011

Role: Assessment and detailed Engineering design of breakwater repairs